HELP - Date Range In 1 Cell Calculation



 
 
Thread Tools Display Modes
  #1  
Old September 15th, 2005, 04:43 PM
Adam
external usenet poster
 
Posts: n/a
Default HELP - Date Range In 1 Cell Calculation

Hello,

I have one cell where i enter a date 8/30/2005 (which resides in A3).

And i need another cell to display a date range based on the above date.
The date range will always be the same number of days apart. For example the
date range will always be 2-7 days from the entered above date. What i did so
far was 2 seperate calculations in 2 different cells. One for the low end
(=SUM(A3+2) and one for the high end =SUM(A3+7). Then I put =(B3) & " " &
"through" & " " & (C3) in the third cell where i want the range to appear.
But what happens is it comes out like:
38596 through 38599

How can i get the dates to remain in date format even though there is text
between them???



  #2  
Old September 15th, 2005, 05:05 PM
Bob Phillips
external usenet poster
 
Posts: n/a
Default

No need for SUM

=A3+2
=A3+7

=TEXT(B3,"m/d/yyy")&" through "&TEXT(C3,"m/d/yyyy")

--
HTH

Bob Phillips

"Adam" wrote in message
...
Hello,

I have one cell where i enter a date 8/30/2005 (which resides in A3).

And i need another cell to display a date range based on the above date.
The date range will always be the same number of days apart. For example

the
date range will always be 2-7 days from the entered above date. What i did

so
far was 2 seperate calculations in 2 different cells. One for the low end
(=SUM(A3+2) and one for the high end =SUM(A3+7). Then I put =(B3) & " " &
"through" & " " & (C3) in the third cell where i want the range to appear.
But what happens is it comes out like:
38596 through 38599

How can i get the dates to remain in date format even though there is text
between them???





  #3  
Old September 15th, 2005, 06:59 PM
Adam
external usenet poster
 
Posts: n/a
Default

Thanks Bob that worked great!

I got one more question:
What if my date range result lands on a weekend and i don't want it to?

Is there a way that i can identify and check that that the result is a
weekend and if it is move the range to the next earliest range?

If possible please use my work email as well ).

Thanks.

"Bob Phillips" wrote:

No need for SUM

=A3+2
=A3+7

=TEXT(B3,"m/d/yyy")&" through "&TEXT(C3,"m/d/yyyy")

--
HTH

Bob Phillips

"Adam" wrote in message
...
Hello,

I have one cell where i enter a date 8/30/2005 (which resides in A3).

And i need another cell to display a date range based on the above date.
The date range will always be the same number of days apart. For example

the
date range will always be 2-7 days from the entered above date. What i did

so
far was 2 seperate calculations in 2 different cells. One for the low end
(=SUM(A3+2) and one for the high end =SUM(A3+7). Then I put =(B3) & " " &
"through" & " " & (C3) in the third cell where i want the range to appear.
But what happens is it comes out like:
38596 through 38599

How can i get the dates to remain in date format even though there is text
between them???






  #4  
Old September 16th, 2005, 12:05 AM
Bob Phillips
external usenet poster
 
Posts: n/a
Default

Now you know that you can g

=TEXT(IF(WEEKDAY(B3,2)6,B3,B3+(8-WEEKDAY(B3,2))),"m/d/yyy")&" through
"&TEXT(IF(WEEKDAY(C3,2)6,C3,C3+(8-WEEKDAY(C3,2))),"m/d/yyyy")

--
HTH

Bob Phillips

"Adam" wrote in message
...
Thanks Bob that worked great!

I got one more question:
What if my date range result lands on a weekend and i don't want it to?

Is there a way that i can identify and check that that the result is a
weekend and if it is move the range to the next earliest range?

If possible please use my work email as well ).

Thanks.

"Bob Phillips" wrote:

No need for SUM

=A3+2
=A3+7

=TEXT(B3,"m/d/yyy")&" through "&TEXT(C3,"m/d/yyyy")

--
HTH

Bob Phillips

"Adam" wrote in message
...
Hello,

I have one cell where i enter a date 8/30/2005 (which resides in A3).

And i need another cell to display a date range based on the above

date.
The date range will always be the same number of days apart. For

example
the
date range will always be 2-7 days from the entered above date. What i

did
so
far was 2 seperate calculations in 2 different cells. One for the low

end
(=SUM(A3+2) and one for the high end =SUM(A3+7). Then I put =(B3) & "

" &
"through" & " " & (C3) in the third cell where i want the range to

appear.
But what happens is it comes out like:
38596 through 38599

How can i get the dates to remain in date format even though there is

text
between them???








  #5  
Old September 19th, 2005, 05:45 PM
Adam
external usenet poster
 
Posts: n/a
Default

Hello Bob,

I used your earlier suggestion of not using the sum and did
=TEXT(B3,"m/d/yyy")&" through "&TEXT(C3,"m/d/yyyy") instead.
I just modified it a little to say:
=TEXT(B3-7,"m/d/yyy")&" through "&TEXT(B3-2,"m/d/yyyy")
This allowed me to use only one cell instead of 2.

Then when you sent me the response to my "check and avoid the weekend"
question the formula did not work. I think because the original solution was
using 2 cells to figure out the range instead of 1 ex:
=TEXT(B3,"m/d/yyy")&" through "&TEXT(C3,"m/d/yyyy")

Is there any way to change
=TEXT(IF(WEEKDAY(B3,2)6,B3,B3+(8-WEEKDAY(B3,2))),"m/d/yyy")&" through
"&TEXT(IF(WEEKDAY(C3,2)6,C3,C3+(8-WEEKDAY(C3,2))),"m/d/yyyy")


to refer only to one cell. I'm trying only referenceing one cell but it is
not working, I may be using the function wrong or fully understand how the
arguments work???

Help if possible..


"Bob Phillips" wrote:

Now you know that you can g

=TEXT(IF(WEEKDAY(B3,2)6,B3,B3+(8-WEEKDAY(B3,2))),"m/d/yyy")&" through
"&TEXT(IF(WEEKDAY(C3,2)6,C3,C3+(8-WEEKDAY(C3,2))),"m/d/yyyy")

--
HTH

Bob Phillips

"Adam" wrote in message
...
Thanks Bob that worked great!

I got one more question:
What if my date range result lands on a weekend and i don't want it to?

Is there a way that i can identify and check that that the result is a
weekend and if it is move the range to the next earliest range?

If possible please use my work email as well ).

Thanks.

"Bob Phillips" wrote:

No need for SUM

=A3+2
=A3+7

=TEXT(B3,"m/d/yyy")&" through "&TEXT(C3,"m/d/yyyy")

--
HTH

Bob Phillips

"Adam" wrote in message
...
Hello,

I have one cell where i enter a date 8/30/2005 (which resides in A3).

And i need another cell to display a date range based on the above

date.
The date range will always be the same number of days apart. For

example
the
date range will always be 2-7 days from the entered above date. What i

did
so
far was 2 seperate calculations in 2 different cells. One for the low

end
(=SUM(A3+2) and one for the high end =SUM(A3+7). Then I put =(B3) & "

" &
"through" & " " & (C3) in the third cell where i want the range to

appear.
But what happens is it comes out like:
38596 through 38599

How can i get the dates to remain in date format even though there is

text
between them???









  #6  
Old September 19th, 2005, 06:35 PM
Bob Phillips
external usenet poster
 
Posts: n/a
Default

Hi Adam,

How about this

=TEXT(IF(WEEKDAY(A3+2,2)6,A3+2,A3+2+(8-WEEKDAY(A3+2,2))),"m/d/yyy")&"
through
"&TEXT(IF(WEEKDAY(A3+7,2)6,A3+7,A3+7+(8-WEEKDAY(A3+7,2))),"m/d/yyyy")

--
HTH

Bob Phillips

"Adam" wrote in message
...
Hello Bob,

I used your earlier suggestion of not using the sum and did
=TEXT(B3,"m/d/yyy")&" through "&TEXT(C3,"m/d/yyyy") instead.
I just modified it a little to say:
=TEXT(B3-7,"m/d/yyy")&" through "&TEXT(B3-2,"m/d/yyyy")
This allowed me to use only one cell instead of 2.

Then when you sent me the response to my "check and avoid the weekend"
question the formula did not work. I think because the original solution

was
using 2 cells to figure out the range instead of 1 ex:
=TEXT(B3,"m/d/yyy")&" through "&TEXT(C3,"m/d/yyyy")

Is there any way to change
=TEXT(IF(WEEKDAY(B3,2)6,B3,B3+(8-WEEKDAY(B3,2))),"m/d/yyy")&" through
"&TEXT(IF(WEEKDAY(C3,2)6,C3,C3+(8-WEEKDAY(C3,2))),"m/d/yyyy")


to refer only to one cell. I'm trying only referenceing one cell but it is
not working, I may be using the function wrong or fully understand how the
arguments work???

Help if possible..


"Bob Phillips" wrote:

Now you know that you can g

=TEXT(IF(WEEKDAY(B3,2)6,B3,B3+(8-WEEKDAY(B3,2))),"m/d/yyy")&" through
"&TEXT(IF(WEEKDAY(C3,2)6,C3,C3+(8-WEEKDAY(C3,2))),"m/d/yyyy")

--
HTH

Bob Phillips

"Adam" wrote in message
...
Thanks Bob that worked great!

I got one more question:
What if my date range result lands on a weekend and i don't want it

to?

Is there a way that i can identify and check that that the result is a
weekend and if it is move the range to the next earliest range?

If possible please use my work email as well ).

Thanks.

"Bob Phillips" wrote:

No need for SUM

=A3+2
=A3+7

=TEXT(B3,"m/d/yyy")&" through "&TEXT(C3,"m/d/yyyy")

--
HTH

Bob Phillips

"Adam" wrote in message
...
Hello,

I have one cell where i enter a date 8/30/2005 (which resides in

A3).

And i need another cell to display a date range based on the above

date.
The date range will always be the same number of days apart. For

example
the
date range will always be 2-7 days from the entered above date.

What i
did
so
far was 2 seperate calculations in 2 different cells. One for the

low
end
(=SUM(A3+2) and one for the high end =SUM(A3+7). Then I put =(B3)

& "
" &
"through" & " " & (C3) in the third cell where i want the range to

appear.
But what happens is it comes out like:
38596 through 38599

How can i get the dates to remain in date format even though there

is
text
between them???











  #7  
Old September 19th, 2005, 08:24 PM
Adam
external usenet poster
 
Posts: n/a
Default

This is working - at least to some extent...I'm trying to test it but i think
i'm confusing myself. Sorry to be such a pain but let me give you this
hypthetical situation and let me if the below formula would work because
right not it's still giving me date ranges that include a weekend.

My real life cell that I'm using is J30. I'm entering August 25th in there,
but my range result is 8/18 - 8/23 which include the 20th and 21st (sat and
sun). When i enter the 25th (or any date) and the range lands on a weekend
like this example, i want to skip around it. I tried using 2-5 day range
instead of 2-7 but it didn't help.
It looks like its checking the range result but not moving it once it
changes???

"Bob Phillips" wrote:

Hi Adam,

How about this

=TEXT(IF(WEEKDAY(A3+2,2)6,A3+2,A3+2+(8-WEEKDAY(A3+2,2))),"m/d/yyy")&"
through
"&TEXT(IF(WEEKDAY(A3+7,2)6,A3+7,A3+7+(8-WEEKDAY(A3+7,2))),"m/d/yyyy")

--
HTH

Bob Phillips

"Adam" wrote in message
...
Hello Bob,

I used your earlier suggestion of not using the sum and did
=TEXT(B3,"m/d/yyy")&" through "&TEXT(C3,"m/d/yyyy") instead.
I just modified it a little to say:
=TEXT(B3-7,"m/d/yyy")&" through "&TEXT(B3-2,"m/d/yyyy")
This allowed me to use only one cell instead of 2.

Then when you sent me the response to my "check and avoid the weekend"
question the formula did not work. I think because the original solution

was
using 2 cells to figure out the range instead of 1 ex:
=TEXT(B3,"m/d/yyy")&" through "&TEXT(C3,"m/d/yyyy")

Is there any way to change
=TEXT(IF(WEEKDAY(B3,2)6,B3,B3+(8-WEEKDAY(B3,2))),"m/d/yyy")&" through
"&TEXT(IF(WEEKDAY(C3,2)6,C3,C3+(8-WEEKDAY(C3,2))),"m/d/yyyy")


to refer only to one cell. I'm trying only referenceing one cell but it is
not working, I may be using the function wrong or fully understand how the
arguments work???

Help if possible..


"Bob Phillips" wrote:

Now you know that you can g

=TEXT(IF(WEEKDAY(B3,2)6,B3,B3+(8-WEEKDAY(B3,2))),"m/d/yyy")&" through
"&TEXT(IF(WEEKDAY(C3,2)6,C3,C3+(8-WEEKDAY(C3,2))),"m/d/yyyy")

--
HTH

Bob Phillips

"Adam" wrote in message
...
Thanks Bob that worked great!

I got one more question:
What if my date range result lands on a weekend and i don't want it

to?

Is there a way that i can identify and check that that the result is a
weekend and if it is move the range to the next earliest range?

If possible please use my work email as well ).

Thanks.

"Bob Phillips" wrote:

No need for SUM

=A3+2
=A3+7

=TEXT(B3,"m/d/yyy")&" through "&TEXT(C3,"m/d/yyyy")

--
HTH

Bob Phillips

"Adam" wrote in message
...
Hello,

I have one cell where i enter a date 8/30/2005 (which resides in

A3).

And i need another cell to display a date range based on the above
date.
The date range will always be the same number of days apart. For
example
the
date range will always be 2-7 days from the entered above date.

What i
did
so
far was 2 seperate calculations in 2 different cells. One for the

low
end
(=SUM(A3+2) and one for the high end =SUM(A3+7). Then I put =(B3)

& "
" &
"through" & " " & (C3) in the third cell where i want the range to
appear.
But what happens is it comes out like:
38596 through 38599

How can i get the dates to remain in date format even though there

is
text
between them???












 




Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is Off
HTML code is Off
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
Copy Cat Ain't Working shep Setting Up & Running Reports 15 September 12th, 2005 05:14 PM
Help PLEASE! Not sure what answer is: Match? Index? Other? baz Worksheet Functions 7 September 3rd, 2005 03:47 PM
Possible Lookup Table Karen Worksheet Functions 5 June 8th, 2005 09:43 PM
Query for 'confirmation' rogge Running & Setting Up Queries 8 April 19th, 2005 03:26 PM
Formula help Wally Worksheet Functions 6 December 5th, 2003 01:18 PM


All times are GMT +1. The time now is 12:20 AM.


Powered by vBulletin® Version 3.6.4
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 OfficeFrustration.
The comments are property of their posters.