How do I add (say 13) working days to an existing date?
Hi
How do I add (say 13) working days to an existing date? With thanks Ship Shiperton Henethe |
#2
|
|||
|
|||
How do I add (say 13) working days to an existing date?
Assuming your existing date is an actual date (i.e.: not formatted as text).
A1: existing date A2: =A1+13 -- John C "ship" wrote: Hi How do I add (say 13) working days to an existing date? With thanks Ship Shiperton Henethe |
#3
|
|||
|
|||
How do I add (say 13) working days to an existing date?
=WORKDAY(A1,13)
Where A1 holds the date Read up on WORKDAY in help, it is part of the Analysis ToolPak that comes with Excel/Office and you can set public holidays for instance in a range of cell and include that range -- Regards, Peo Sjoblom "ship" wrote in message ... Hi How do I add (say 13) working days to an existing date? With thanks Ship Shiperton Henethe |
#4
|
|||
|
|||
How do I add (say 13) working days to an existing date?
ignore my post
-- John C "John C" wrote: Assuming your existing date is an actual date (i.e.: not formatted as text). A1: existing date A2: =A1+13 -- John C "ship" wrote: Hi How do I add (say 13) working days to an existing date? With thanks Ship Shiperton Henethe |