Can I enter multiple dates for a task in Visio Gantt?
I need to enter multiple dates under one task in a Gantt chart. Can I do
that? If so , how? Ex. 7/20/09 - 7/24/09 and then again 8/17/09 - 9/11/09 |
#2
|
|||
|
|||
Can I enter multiple dates for a task in Visio Gantt?
I don't believe Visio's Gantt chart allows you to do this. Microsoft Project
does allow you to "split" a task. Wapperdude "Danielle" wrote: I need to enter multiple dates under one task in a Gantt chart. Can I do that? If so , how? Ex. 7/20/09 - 7/24/09 and then again 8/17/09 - 9/11/09 |