On Feb 23, 1:05*pm, KARL DEWEY
wrote:
I assume I need to split the Location field into its own table


You did not say how your table(s) is structured now - field names with
datatype or provide sample data.
How will you use the Size? *Will you be adding or multiplying by some other
factors?

How would I go about correcting the existing estimates that have no location sizes entered.


Not knowing the above I would guess to set all old records = 0.

--
Build a little, test a little.



"Shannon" wrote:
I have a table of estimates. Each estimate can have multiple locations
stored as a text field. New need: I want to store the sizes of each
location. Example is -Old method: EstNo= 200 which has Location =
bedroom, Location= Family room. * *New need is: *EstNo 200, *Location
= bedroom *with Size= 100 *and Location= Family room size = 125. *I
assume I need to split the Location field into its own table with a
Location ID field, Location field, location size field and EstNo
field. Also, How would I go about correcting the existing estimates
that have no location sizes entered. * Hope I discribed this clearly
as I am a newby.
.- Hide quoted text -


- Show quoted text -


Thanks for the response and here is the info requested.
tblBidInfo
EstNo=number
Descrip=txt
JobCatId= lookup table txt
Other misc fields

tblBidDet
BidId= autonum
EstNo-=number ~ linked to tblBidInfo
Location= txt values recvd from lookup table
Other misc fields

I was thinking I need to add a new tblLocations with the following
fields,
LocId = autonum
LocName = txt ~ recvd from exisitng Lookup table of txt listings

I get confused here.
I will be using Location size in simple math calcs. Basically Estno
2010.1 has a bedroom thats 100 sf. All the listed work in that
location will be reported and then calculated on the size [ bedroom
work costs 8,000 / 100 sf = 80 psf cost. There are other calcs and
percentage operations I will do in reports based upon that data.]